Location
Kirkop, Malta
-
Role
EPCM Contractor
-
Life Cycle Contract
4 months, 2014
-
Total Contract Value
Euro 0.6M
SCOPE OF WORK
STmicroelectronics contracted FMcore to provide new MEP services for their back end testing facility. The project necessitated a larger cooling demand together with a different typology. Services which were fed from below ground were dismantled, raised floor removed and new services fitted over the suspended ceiling. The services included new HVAC designed to attain a 400W/m2 load criteria, new compressed, vacuum and chilled water pipework. Pressurised air into the building was provided by a dedicated AHU.
.